Question
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order . What do you have to consider?
Options
- AThe maintenance orders must be assigned to WBS element.
- BThe maintenance order s must be assigned to the same budget profile as the project definition.
- CThe maintenance orders must be assigned as sub-networks.
- DThe maintenance orders must be assigned to the same plant as the network.