C_TS412_2021 · Question #64

You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order . What do you have to consider?

The correct answer is A. The maintenance orders must be assigned to WBS element. To schedule both the network and the maintenance orders, you have to consider that the maintenance orders must be assigned to WBS elements. This means that you have to link the maintenance orders to WBS elements in your project structure using assignment objects. This way, you…

Project Structures

Question

You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order . What do you have to consider?

Options

  • AThe maintenance orders must be assigned to WBS element.
  • BThe maintenance order s must be assigned to the same budget profile as the project definition.
  • CThe maintenance orders must be assigned as sub-networks.
  • DThe maintenance orders must be assigned to the same plant as the network.

How the community answered

(25 responses)
  • A
    84% (21)
  • B
    4% (1)
  • C
    4% (1)
  • D
    8% (2)

Explanation

To schedule both the network and the maintenance orders, you have to consider that the maintenance orders must be assigned to WBS elements. This means that you have to link the maintenance orders to WBS elements in your project structure using assignment objects. This way, you can ensure that the dates of the maintenance orders are synchronized with the dates of the WBS elements and the network activities. You can also use overall network scheduling to schedule several networks and maintenance orders together.

Topics

#WBS structure#network scheduling#maintenance order#project scheduling