C_TS412_2021 · Question #63
How can the system activate requirements (such as reservations or purchase requisitions)? Note: There are 2 correct answers to this question
The correct answer is A. Immediately, by saving the project D. When releasing a network or an activity. The system can activate requirements (such as reservations or purchase requisitions) in different ways, depending on the settings in customizing and master data. Some of these ways are: Immediately, by saving the project: This means that the system creates requirements for all…
Question
How can the system activate requirements (such as reservations or purchase requisitions)? Note:
There are 2 correct answers to this question
Options
- AImmediately, by saving the project
- BAutomatically, using the requirement date and the replenishment lead time
- CUsing a standard milestone activity
- DWhen releasing a network or an activity
How the community answered
(32 responses)- A81% (26)
- B6% (2)
- C13% (4)
Explanation
The system can activate requirements (such as reservations or purchase requisitions) in different ways, depending on the settings in customizing and master data. Some of these ways are: Immediately, by saving the project: This means that the system creates requirements for all materials assigned to WBS elements or activities as soon as you save the project. This option requires that you set the indicator "Requirements immediately" in customizing for your project profile. When releasing a network or an activity: This means that the system creates requirements for all materials assigned to a network or an activity when you release them. This option requires that you set the indicator "Requirements on release" in customizing for your network type or
Topics