A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
The correct answer is B. Costing Sheet. To allocate overhead rates to a WBS element, you must assign a costing sheet to the WBS element. A costing sheet is a tool that allows you to define and calculate overhead costs based on various criteria, such as plant, company code, material origin, or order type. You can…
Question
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
Options
- ASettlement rules
- BCosting Sheet
- CInvestment profile.
- DResults analysis key
How the community answered
(29 responses)- A3% (1)
- B93% (27)
- C3% (1)
Explanation
To allocate overhead rates to a WBS element, you must assign a costing sheet to the WBS element. A costing sheet is a tool that allows you to define and calculate overhead costs based on various criteria, such as plant, company code, material origin, or order type. You can assign a costing sheet to a WBS element in the Control Data tab of the WBS element master data.