nerdexam
SAP

C_TS412_2021 · Question #18

You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

The correct answer is D. Planning of overall values. Planning of overall values (D) lets you assign a single lump-sum cost figure directly to a WBS element without mapping it to any cost elements - it's the most minimal and accessible costing method in SAP PS, perfectly matching both requirements: ease of use and no cost element…

Costs and Revenues in Project Systems

Question

You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?

Options

  • AUnit costing for WBS
  • BEasy Cost Planning (ECP) for WBS
  • CDetailed planning for WBS
  • DPlanning of overall values

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    10% (3)
  • D
    87% (26)

Explanation

Planning of overall values (D) lets you assign a single lump-sum cost figure directly to a WBS element without mapping it to any cost elements - it's the most minimal and accessible costing method in SAP PS, perfectly matching both requirements: ease of use and no cost element dependency.

Why the distractors are wrong:

  • (A) Unit costing is structured around line items (materials, activities, etc.) that ultimately map to cost elements, adding complexity.
  • (B) Easy Cost Planning (ECP) sounds like the obvious answer given "easy to use," but ECP uses costing items that are tied to cost elements under the hood - it fails the "no cost elements" requirement.
  • (C) Detailed planning is explicitly cost-element-based (it plans costs by cost element), directly contradicting the requirement.

Memory tip: Think of it as a spectrum - Detailed planning needs cost elements, ECP/Unit costing are middle ground, and Overall values is the "big number only" option. Whenever an exam says "no cost elements + simple," go to the extreme simple end: Overall.

Topics

#WBS costing#overall value planning#cost planning method#Easy Cost Planning

Community Discussion

No community discussion yet for this question.

Full C_TS412_2021 Practice