Which of the following transactions can you use to post actual cost for external processing. Note: there are 2 correct answer for this question.

The correct answer is A. Approval of a service entry sheet D. Approval of a good receipt. The approval of a service entry sheet and the approval of a goods receipt are both transactions that can be used to post actual costs for external processing."

Costs and Revenues in Project Systems

Question

Which of the following transactions can you use to post actual cost for external processing. Note: there are 2 correct answer for this question.

Options

  • AApproval of a service entry sheet
  • BPosting a goods receipt
  • CCreating a service entry sheet
  • DApproval of a good receipt.
  • ECreating a purchase order.

How the community answered

(56 responses)
  • A
    93% (52)
  • B
    4% (2)
  • C
    2% (1)
  • E
    2% (1)

Explanation

The approval of a service entry sheet and the approval of a goods receipt are both transactions that can be used to post actual costs for external processing."

Topics

#actual costs#external processing#service entry sheet#goods receipt