Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

The correct answer is A. Saving a supplier invoice B. Saving a service entry shee. Saving a supplier invoice and saving a service entry sheet are some of the actions that can transfer actual costs for external processing. External processing is a process that involves procuring services from external vendors for project activities. Saving a supplier invoice…

Costs and Revenues in Project Systems

Question

Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

Options

  • ASaving a supplier invoice
  • BSaving a service entry shee
  • CSaving a goods receipt
  • DSaving a purchase order

How the community answered

(18 responses)
  • A
    94% (17)
  • D
    6% (1)

Explanation

Saving a supplier invoice and saving a service entry sheet are some of the actions that can transfer actual costs for external processing. External processing is a process that involves procuring services from external vendors for project activities. Saving a supplier invoice is an action that records the payment request from a vendor for the services performed and posts actual costs to the project. Saving a service entry sheet is an action that records the delivery of services from a vendor and posts actual costs to the project.

Topics

#external processing#actual costs#supplier invoice#service entry sheet