C_TS412_2021 · Question #9
Which object is used to allocate the costs from a claim to the project structure?
The correct answer is D. WBS element. A WBS element is an object that is used to allocate the costs from a claim to the project structure. A claim is a document that records a customer's request for compensation due to deviations from the agreed terms and conditions of a project. A WBS element is a structural…
Question
Which object is used to allocate the costs from a claim to the project structure?
Options
- ANetwork activity
- BInternal order
- CClaim
- DWBS element
How the community answered
(38 responses)- A8% (3)
- C3% (1)
- D89% (34)
Explanation
A WBS element is an object that is used to allocate the costs from a claim to the project structure. A claim is a document that records a customer's request for compensation due to deviations from the agreed terms and conditions of a project. A WBS element is a structural element of a project that represents a task or a partial task. You can assign claims to WBS elements and post costs or revenues to them.
Topics
Community Discussion
No community discussion yet for this question.