C_TS412_2021 · Question #9

Which object is used to allocate the costs from a claim to the project structure?

The correct answer is D. WBS element. A WBS element is an object that is used to allocate the costs from a claim to the project structure. A claim is a document that records a customer's request for compensation due to deviations from the agreed terms and conditions of a project. A WBS element is a structural…

Costs and Revenues in Project Systems

Question

Which object is used to allocate the costs from a claim to the project structure?

Options

  • ANetwork activity
  • BInternal order
  • CClaim
  • DWBS element

How the community answered

(38 responses)
  • A
    8% (3)
  • C
    3% (1)
  • D
    89% (34)

Explanation

A WBS element is an object that is used to allocate the costs from a claim to the project structure. A claim is a document that records a customer's request for compensation due to deviations from the agreed terms and conditions of a project. A WBS element is a structural element of a project that represents a task or a partial task. You can assign claims to WBS elements and post costs or revenues to them.

Topics

#claim management#cost allocation#WBS element#project structure