C_TS412_2021 · Question #74
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
The correct answer is B. You can also represent a project using a WBS and one or more networks. C. You can create a project based on a Activity. You can use both WBS and networks to represent a project in SAP S/4HANA Project System. A WBS shows the hierarchical structure of the project, while a network shows the flow and dependencies of the project activities." According to SAP Blogs3, "You can create a project based on…
Question
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
Options
- AYou can map a project using only one WBS or one network.
- BYou can also represent a project using a WBS and one or more networks.
- CYou can create a project based on a Activity.
- DYou cannot use the characteristics of both the structures (WBS and Networks) together to
How the community answered
(49 responses)- A4% (2)
- B94% (46)
- D2% (1)
Explanation
You can use both WBS and networks to represent a project in SAP S/4HANA Project System. A WBS shows the hierarchical structure of the project, while a network shows the flow and dependencies of the project activities." According to SAP Blogs3, "You can create a project based on an activity by using the app `Create Project from Activity'."