Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

The correct answer is B. You can also represent a project using a WBS and one or more networks. C. You can create a project based on a Activity. You can use both WBS and networks to represent a project in SAP S/4HANA Project System. A WBS shows the hierarchical structure of the project, while a network shows the flow and dependencies of the project activities." According to SAP Blogs3, "You can create a project based on…

Project Structures

Question

Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

Options

  • AYou can map a project using only one WBS or one network.
  • BYou can also represent a project using a WBS and one or more networks.
  • CYou can create a project based on a Activity.
  • DYou cannot use the characteristics of both the structures (WBS and Networks) together to

How the community answered

(49 responses)
  • A
    4% (2)
  • B
    94% (46)
  • D
    2% (1)

Explanation

You can use both WBS and networks to represent a project in SAP S/4HANA Project System. A WBS shows the hierarchical structure of the project, while a network shows the flow and dependencies of the project activities." According to SAP Blogs3, "You can create a project based on an activity by using the app `Create Project from Activity'."