C_TS412_2021 · Question #75
Which statement regarding the creation of a new work breakdown structure (WBS element) are true? Note: there are 3 correct answer for this question.
The correct answer is A. You can create several WBS elements per level. C. A WBS element of the new project can be assigned to a different project definition. D. WBS element can be a planning element, an account assignment element, and a billing element at. You can create several WBS elements per level." According to SAP Help Portal2, "You can assign a WBS element of the new project to a different project definition." According to SAP Help Portal3, "WBS elements can be planning elements, account assignment elements, and billing…
Question
Which statement regarding the creation of a new work breakdown structure (WBS element) are true? Note: there are 3 correct answer for this question.
Options
- AYou can create several WBS elements per level.
- BA new work breakdown structure must contain up to 10 levels.
- CA WBS element of the new project can be assigned to a different project definition.
- DWBS element can be a planning element, an account assignment element, and a billing element at
- EThe WBS structure can contain several level 1 WBS element,
How the community answered
(44 responses)- A91% (40)
- B7% (3)
- E2% (1)
Explanation
You can create several WBS elements per level." According to SAP Help Portal2, "You can assign a WBS element of the new project to a different project definition." According to SAP Help Portal3, "WBS elements can be planning elements, account assignment elements, and billing elements at the same time."