C_TS412_2021 · Question #82
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
The correct answer is A. Material master D. BOM item. To enable automatic assignment of material components to the project, you have to maintain the material master and the BOM item. The material master contains the data required for planning and procurement of materials. The BOM item contains the data required for assigning…
Question
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
Options
- AMaterial master
- BNetwork activity
- CWBS element
- DBOM item
How the community answered
(49 responses)- A94% (46)
- B2% (1)
- C4% (2)
Explanation
To enable automatic assignment of material components to the project, you have to maintain the material master and the BOM item. The material master contains the data required for planning and procurement of materials. The BOM item contains the data required for assigning materials to a network activity or a WBS element.
Topics
Community Discussion
No community discussion yet for this question.