C_TS412_2021 · Question #5
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons…
The correct answer is C. The indicator Reservation/Purchase Requisition indicator for the material component assigned to D. The material is assigned to the activity as a non-stock material. Some possible reasons for the missing reservation for a material component assigned to a network activity are: The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never", which means that no reservation or…
Question
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct answers to this question
Options
- AThe availability check for material components indicates missing parts
- BThe material master is set to external procurement
- CThe indicator Reservation/Purchase Requisition indicator for the material component assigned to
- DThe material is assigned to the activity as a non-stock material
How the community answered
(45 responses)- A9% (4)
- B7% (3)
- C84% (38)
Explanation
Some possible reasons for the missing reservation for a material component assigned to a network activity are: The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never", which means that no reservation or purchase requisition is created for the material component. The material is assigned to the activity as a non-stock material, which means that it does not have a stock record in inventory management and no reservation is created for it.