C_TS412_2021 · Question #6
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do…
The correct answer is B. Enter February 10 as fixed date. To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding…
Question
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
Options
- AEnter an offset of -18 days to the finish date of the activity
- BEnter February 10 as fixed date
- CEnter 10 days as duration
- DEnter an offset of 10 days to the start date of the activity
How the community answered
(48 responses)- A15% (7)
- B75% (36)
- C4% (2)
- D6% (3)
Explanation
To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint.