SAP
C_TS412_2021 · Question #6
C_TS412_2021 Question #6: Real Exam Question with Answer & Explanation
Sign in or unlock C_TS412_2021 to reveal the answer and full explanation for question #6. The question stem and answer options stay visible for context.
Question
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
Options
- AEnter an offset of -18 days to the finish date of the activity
- BEnter February 10 as fixed date
- CEnter 10 days as duration
- DEnter an offset of 10 days to the start date of the activity
Unlock C_TS412_2021 to see the answer
You've previewed enough free C_TS412_2021 questions. Unlock C_TS412_2021 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.