C_TS412_2021 · Question #90
C_TS412_2021 Question #90: Real Exam Question with Answer & Explanation
Sign in or unlock C_TS412_2021 to reveal the answer and full explanation for question #90. The question stem and answer options stay visible for context.
Question
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
Options
- AMaintain subordinate internal activity elements assigned to other work centres
- BIncrease the capacities of the work center in the project planning board.
- CTrigger automatic capacity leveling inside the project planning board
- DShift activities backward or forward on the time axis where more capacities are available