C_TS412_2021 · Question #54

How are capacity requirements determined?

The correct answer is C. Using the control key of an activity. Capacity requirements are determined by using the control key of an activity. The control key is an object that defines various control parameters for an activity, such as scheduling type, confirmation type, costing relevance, or capacity requirements determination. The…

Project Planning

Question

How are capacity requirements determined?

Options

  • AIndependent of scheduling and according to the capacity planner group.
  • BUsing scheduling and the capacity category.
  • CUsing the control key of an activity.
  • DUsing scheduling and distribution key.

How the community answered

(42 responses)
  • A
    10% (4)
  • B
    14% (6)
  • C
    71% (30)
  • D
    5% (2)

Explanation

Capacity requirements are determined by using the control key of an activity. The control key is an object that defines various control parameters for an activity, such as scheduling type, confirmation type, costing relevance, or capacity requirements determination. The capacity requirements determination indicator in the control key specifies whether capacity requirements are calculated for an activity based on its work or duration. The capacity requirements are then used for capacity planning and leveling.

Topics

#capacity requirements#control key#scheduling#capacity determination