What is copied when transferring a simulation version back to an operative project?

The correct answer is A. Plan costs B. WBS elements E. Network activities. When transferring a simulation, planning structures and planning data are copied. Actual data and maintenance orders are not overwritten.

Project Planning

Question

What is copied when transferring a simulation version back to an operative project?

Options

  • APlan costs
  • BWBS elements
  • CActual work
  • DMaintenance orders assigned to the project
  • ENetwork activities

How the community answered

(32 responses)
  • A
    94% (30)
  • C
    3% (1)
  • D
    3% (1)

Explanation

When transferring a simulation, planning structures and planning data are copied. Actual data and maintenance orders are not overwritten.

Topics

#simulation version#operative project#WBS elements#network activities