What is copied when transferring a simulation version back to an operative project?
The correct answer is A. Plan costs B. WBS elements E. Network activities. When transferring a simulation, planning structures and planning data are copied. Actual data and maintenance orders are not overwritten.
Project Planning
Question
What is copied when transferring a simulation version back to an operative project?
Options
- APlan costs
- BWBS elements
- CActual work
- DMaintenance orders assigned to the project
- ENetwork activities
How the community answered
(32 responses)- A94% (30)
- C3% (1)
- D3% (1)
Explanation
When transferring a simulation, planning structures and planning data are copied. Actual data and maintenance orders are not overwritten.
Topics
#simulation version#operative project#WBS elements#network activities