C_TS412_2021 · Question #52

Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

The correct answer is B. Project Builder C. Project planning board. To plan basic dates manually for WBS elements, you can use the Project Builder or the Project planning board. These are tools that allow you to create and maintain project structures, such as WBS elements, networks, activities, and milestones. You can enter basic dates for WBS…

Project Planning

Question

Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.

Options

  • ASchedule Manager
  • BProject Builder
  • CProject planning board
  • DEasy Cost Planning

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    89% (40)
  • D
    7% (3)

Explanation

To plan basic dates manually for WBS elements, you can use the Project Builder or the Project planning board. These are tools that allow you to create and maintain project structures, such as WBS elements, networks, activities, and milestones. You can enter basic dates for WBS elements in the Basic Data tab of the WBS element master data in the Project Builder or in the Gantt chart view of the Project planning board.

Topics

#basic dates#WBS element scheduling#Project Builder#project planning board