C_TS412_2021 · Question #24
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?
The correct answer is A. Free planning. To extrapolate the basic dates of subordinate WBS elements without taking into account the basic dates of higher-level WBS elements, you can use free planning as the planning method for basic dates. Free planning is a type of planning method for basic dates that allows you to…
Question
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?
Options
- AFree planning
- BTop-down
- CStrict bottom-up
- DBottom-up
How the community answered
(56 responses)- A93% (52)
- B4% (2)
- C2% (1)
- D2% (1)
Explanation
To extrapolate the basic dates of subordinate WBS elements without taking into account the basic dates of higher-level WBS elements, you can use free planning as the planning method for basic dates. Free planning is a type of planning method for basic dates that allows you to plan dates for WBS elements without any restrictions or dependencies on other WBS elements. Free planning does not consider any hierarchical relationships between WBS elements when calculating their dates. Free planning gives you maximum flexibility and control over your date planning for WBS elements.