C_TS412_2021 · Question #13
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
The correct answer is A. Activity. To maintain constraints for start dates, you can use activities. Activities are structural elements of a network that represent tasks or partial tasks within a project. Constraints are parameters that define fixed dates or time intervals for activities or networks. Constraints…
Question
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
Options
- AActivity
- BNetwork header
- CMilestone
- DActivity element
How the community answered
(36 responses)- A92% (33)
- C3% (1)
- D6% (2)
Explanation
To maintain constraints for start dates, you can use activities. Activities are structural elements of a network that represent tasks or partial tasks within a project. Constraints are parameters that define fixed dates or time intervals for activities or networks. Constraints can be used to influence the scheduling of project objects and to ensure that certain deadlines are met. You can maintain constraints for start dates or finish dates of activities or networks in the project builder or the project planning board.