Question
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
Options
- AThe purchase order can be updated in Goods Receipt for Purchase Order (MIGO)
- BThe purchase order is updated automatically to match the new quantity while saving the project.
- CA workflow can be triggered to inform the purchasing group.
- DThe system automatically creates a new purchase requisition with the difference to the original