SAP
C_TS412_2021 · Question #67
You plan double the work on each internal activity for multiple project. What do you recommend?
The correct answer is A. Use mass change (CNMASS) in the project system. Mass change (CNMASS) is a powerful tool that allows you to change multiple fields in multiple objects at once. You can use it to change fields in project definitions, WBS elements, networks, activities, milestones, and PRTs."
Project Execution
Question
You plan double the work on each internal activity for multiple project. What do you recommend?
Options
- AUse mass change (CNMASS) in the project system.
- BDouble the work of each internal activity, one after another, in the project Builder.
- CDouble the capacity in the work center.
- DUse mass change within the project Builder (CJ20N).
How the community answered
(40 responses)- A90% (36)
- B5% (2)
- C3% (1)
- D3% (1)
Explanation
Mass change (CNMASS) is a powerful tool that allows you to change multiple fields in multiple objects at once. You can use it to change fields in project definitions, WBS elements, networks, activities, milestones, and PRTs."
Topics
#mass change#internal activities#CNMASS#project builder
Community Discussion
No community discussion yet for this question.