C_TS412_2021 · Question #35

Which planning method can prevent further rescheduling of activities?

The correct answer is A. Partial confirmation of activities. Partial confirmation of activities is a planning method that allows you to confirm a part of an activity's duration or work. This prevents further rescheduling of the activity because the confirmed part is fixed and cannot be changed. The remaining part of the activity can…

Project Execution

Question

Which planning method can prevent further rescheduling of activities?

Options

  • APartial confirmation of activities
  • BCapacity requirements activation
  • CCapacity levelling
  • DWorkforce planning

How the community answered

(49 responses)
  • A
    80% (39)
  • B
    12% (6)
  • C
    6% (3)
  • D
    2% (1)

Explanation

Partial confirmation of activities is a planning method that allows you to confirm a part of an activity's duration or work. This prevents further rescheduling of the activity because the confirmed part is fixed and cannot be changed. The remaining part of the activity can still be rescheduled according to the project progress and resource availability.

Topics

#partial confirmation#rescheduling prevention#activity scheduling#project execution