C_TS412_2021 · Question #66
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There are 3 correct…
The correct answer is B. A material master with sales views C. Assignment between material and standard network D. Standard network with activities. According to SAP Press2, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network."
Question
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There are 3 correct answers to this question
Options
- AA bill of material with sales views
- BA material master with sales views
- CAssignment between material and standard network
- DStandard network with activities
- EA production order
How the community answered
(55 responses)- A13% (7)
- B82% (45)
- E5% (3)
Explanation
According to SAP Press2, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network."