C_TS412_2021 · Question #66

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There are 3 correct…

The correct answer is B. A material master with sales views C. Assignment between material and standard network D. Standard network with activities. According to SAP Press2, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network."

Project Execution

Question

You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There are 3 correct answers to this question

Options

  • AA bill of material with sales views
  • BA material master with sales views
  • CAssignment between material and standard network
  • DStandard network with activities
  • EA production order

How the community answered

(55 responses)
  • A
    13% (7)
  • B
    82% (45)
  • E
    5% (3)

Explanation

According to SAP Press2, "To use assembly processing, you need a material master with sales views, a bill of material (BOM) for the material, a standard network with activities, and an assignment between the material and the standard network."

Topics

#assembly processing#sales order#standard network#material master