The correct answer is D. Event scenarios must be defined.. To implement scheduling of events, event scenarios must be defined. Event scenarios are predefined sets of events that describe typical sequences of activities in a project. Events are points in time that mark the start or finish of an activity or a milestone. Event scenarios can

Question

Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events. What is the requisites for implement scheduling of events?

Options

  • APriority of events must be set.
  • BScheduling parameters for material scheduling must be set.
  • CEvents must be released manually.
  • DEvent scenarios must be defined.

Explanation

To implement scheduling of events, event scenarios must be defined. Event scenarios are predefined sets of events that describe typical sequences of activities in a project. Events are points in time that mark the start or finish of an activity or a milestone. Event scenarios can be used to schedule events automatically based on their dependencies and priorities. Event scenarios can also be used to track and monitor the progress of events in a project.