C_TS412_2021 · Question #56
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason? Note: there…
The correct answer is A. The procurement type in the material master is set to in-house Production. C. The material have no material number. To create purchase requisitions for the materials used in your project, you must ensure that the materials have a procurement type that allows external procurement and a material number that identifies them uniquely. Some of the possible reasons why no purchase requisitions…
Question
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason? Note:
there are 2 correct answers for this question.
Options
- AThe procurement type in the material master is set to in-house Production.
- BThe item category of the materials is set tstock item.
- CThe material have no material number.
- DThe item category of the materials is set tnon-stock item.
How the community answered
(53 responses)- A81% (43)
- B13% (7)
- D6% (3)
Explanation
To create purchase requisitions for the materials used in your project, you must ensure that the materials have a procurement type that allows external procurement and a material number that identifies them uniquely. Some of the possible reasons why no purchase requisitions have been created after releasing the project are: The procurement type in the material master is set to in-house production (E). This means that the material is produced internally and not procured externally from a vendor. The material has no material number (N). This means that the material is a non-stock item that is not managed in inventory and has no master record. Non-stock items require manual creation of purchase
Topics