C_TS412_2021 · Question #80

How can material components be assigned to network activities?

The correct answer is A. Using manual assignment B. Using the bill of materials transfer E. Using the Internet-based catalog. Material components can be assigned: Manually in the network activity By transferring a bill of materials Using an Internet-based procurement catalog Sales orders and ProMan do not directly assign material components to activities.

Materials in Project Systems

Question

How can material components be assigned to network activities?

Options

  • AUsing manual assignment
  • BUsing the bill of materials transfer
  • CUsing assigned sales orders
  • DUsing Project-Oriented Procurement (ProMan)
  • EUsing the Internet-based catalog

How the community answered

(30 responses)
  • A
    90% (27)
  • C
    3% (1)
  • D
    7% (2)

Explanation

Material components can be assigned: Manually in the network activity By transferring a bill of materials Using an Internet-based procurement catalog Sales orders and ProMan do not directly assign material components to activities.

Topics

#material components#network activities#BOM transfer#catalog assignment