Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question
The correct answer is A. The materials must allow sales order or project stock D. An MRP group must be assigned. Requirements grouping of materials is a process that allows you to plan and procure materials jointly for several WBS elements within a project or across projects. To use requirements grouping of materials, the materials must allow sales order or project stock, which means they…
Question
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question
Options
- AThe materials must allow sales order or project stock
- BThe exact lot size procedure must be used
- CThe procurement type of the material must be internal
- DAn MRP group must be assigned
How the community answered
(37 responses)- A70% (26)
- B19% (7)
- C11% (4)
Explanation
Requirements grouping of materials is a process that allows you to plan and procure materials jointly for several WBS elements within a project or across projects. To use requirements grouping of materials, the materials must allow sales order or project stock, which means they must have a special procurement type of E or Q in the material master. An MRP group must also be assigned to the materials, which defines the parameters for material requirements planning, such as lot size and planning strategy.