C_TS412_2021 · Question #79
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network…
The correct answer is C. The normal duration of each activity is missing. If an activity has no normal duration, the system schedules it with zero length. As a result, all activities receive the same start and finish dates as the network header.
Project Planning
Question
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Options
- AThe control key is set to no scheduling
- BThe scheduling type is set to capacity requirements only
- CThe normal duration of each activity is missing
- DThere is a loop in the network
How the community answered
(54 responses)- A9% (5)
- B4% (2)
- C70% (38)
- D17% (9)
Explanation
If an activity has no normal duration, the system schedules it with zero length. As a result, all activities receive the same start and finish dates as the network header.
Topics
#network scheduling#activity duration#Gantt chart#scheduling diagnosis