C_TS412_2021 · Question #78

When using budgeting and active availability control, which business transactions affect the current budget?

The correct answer is B. Original budget D. Transfers E. Supplements. The current budget in SAP Project System is calculated from all approved budget transactions, including original budget, budget supplements, and budget transfers. Cost planning and revenues do not influence the budget used for availability control.

Project Budgeting

Question

When using budgeting and active availability control, which business transactions affect the current budget?

Options

  • ACost element planning
  • BOriginal budget
  • CRevenues
  • DTransfers
  • ESupplements

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    91% (41)
  • C
    7% (3)

Explanation

The current budget in SAP Project System is calculated from all approved budget transactions, including original budget, budget supplements, and budget transfers. Cost planning and revenues do not influence the budget used for availability control.

Topics

#availability control#current budget#supplements#budget transfers