You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget

The correct answer is D. Availability control. Availability control is a function that can be used to check assigned values against the current budget for WBS elements within your project. Availability control is a process that monitors whether budget overruns occur in your project and issues warnings or error messages if…

Project Budgeting

Question

You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget

Options

  • AResults analysis
  • BEasy Cost Planning
  • CCost forecast
  • DAvailability control

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • D
    89% (25)

Explanation

Availability control is a function that can be used to check assigned values against the current budget for WBS elements within your project. Availability control is a process that monitors whether budget overruns occur in your project and issues warnings or error messages if predefined tolerance limits are exceeded. You can activate availability control for individual WBS elements or for entire projects and define different tolerance limits for different types of costs or