Question
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
Options
- AActivate availability control for the WBS elements. Define the tolerance limits on each WBS
- BActivate availability control in the assigned budget profile. Define the tolerance limits in
- CActivate commitment management in the project definition Enter the budget in the master data of
- DActivate availability control for projects in the controlling area. Enter the plan data for each WBS