C_TS412_2021 · Question #100
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
The correct answer is D. Basic dates of the network activity. To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and…
Question
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
Options
- AActual dates of the network activity
- BBasic dates of the WBS
- CForecast dates of the WBS
- DBasic dates of the network activity
How the community answered
(39 responses)- A8% (3)
- B3% (1)
- C3% (1)
- D87% (34)
Explanation
To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. The requirement date for a material component is derived from the basic start date of the activity to which it is assigned.