nerdexam
SAP

C_TS412_2021 · Question #100

You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

The correct answer is D. Basic dates of the network activity. To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and…

Materials in Project Systems

Question

You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?

Options

  • AActual dates of the network activity
  • BBasic dates of the WBS
  • CForecast dates of the WBS
  • DBasic dates of the network activity

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    3% (1)
  • D
    87% (34)

Explanation

To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. The requirement date for a material component is derived from the basic start date of the activity to which it is assigned.

Topics

#requirement date#network activity#basic dates#material assignment

Community Discussion

No community discussion yet for this question.

Full C_TS412_2021 Practice