nerdexam
SAP

C_TS412_2021 · Question #70

C_TS412_2021 Question #70: Real Exam Question with Answer & Explanation

The correct answer is C. Activate availability control in the assign budget profile. Defined the tolerance limit in the. You can use availability control to monitor budgets for projects or parts of projects (WBS elements). Availability control checks whether sufficient funds are available for planned or actual costs. If the budget is exceeded by a certain percentage (tolerance limit), the system is

Question

A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget. What action do you have tsolve the problem?

Options

  • AActivate availability control For projects in the control area. Enter the plan data for each WBS
  • BActivate availability control for the important WBS element. Define the tolerance limit on each WBS
  • CActivate availability control in the assign budget profile. Defined the tolerance limit in the
  • Dmanagement in the project definition. Enter the budget in the master data of the top WBS element.

Explanation

You can use availability control to monitor budgets for projects or parts of projects (WBS elements). Availability control checks whether sufficient funds are available for planned or actual costs. If the budget is exceeded by a certain percentage (tolerance limit), the system issues a warning or an error message.

Community Discussion

No community discussion yet for this question.

Full C_TS412_2021 Practice