C_TS412_2021 · Question #70
C_TS412_2021 Question #70: Real Exam Question with Answer & Explanation
The correct answer is C. Activate availability control in the assign budget profile. Defined the tolerance limit in the. You can use availability control to monitor budgets for projects or parts of projects (WBS elements). Availability control checks whether sufficient funds are available for planned or actual costs. If the budget is exceeded by a certain percentage (tolerance limit), the system is
Question
Options
- AActivate availability control For projects in the control area. Enter the plan data for each WBS
- BActivate availability control for the important WBS element. Define the tolerance limit on each WBS
- CActivate availability control in the assign budget profile. Defined the tolerance limit in the
- Dmanagement in the project definition. Enter the budget in the master data of the top WBS element.
Explanation
You can use availability control to monitor budgets for projects or parts of projects (WBS elements). Availability control checks whether sufficient funds are available for planned or actual costs. If the budget is exceeded by a certain percentage (tolerance limit), the system issues a warning or an error message.
Community Discussion
No community discussion yet for this question.