C_TS412_2021 · Question #92

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

The correct answer is B. You can always maintain the actual start if the WBS element has the status "Released" or C. You can always maintain the actual start and finish date of a WBS element. If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially…

Project Execution

Question

You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question

Options

  • AYou can only maintain the actual finish if all lower-level WBS elements have an actual finish date
  • BYou can always maintain the actual start if the WBS element has the status "Released" or
  • CYou can always maintain the actual start and finish date of a WBS element
  • DYou can only maintain the actual start of a WBS element if the finish date is not maintained

How the community answered

(42 responses)
  • A
    19% (8)
  • B
    74% (31)
  • D
    7% (3)

Explanation

If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially released", which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element.

Topics

#actual dates#WBS elements#project status#actual start finish