C_TS412_2021 · Question #94
C_TS412_2021 Question #94: Real Exam Question with Answer & Explanation
The correct answer is A. A work center has not been assigned to the activity B. The work center does not contain any available capacity data D. The indicator that calculates capacity requirements is deactivated in the header of the network. Capacity requirements cannot be calculated if: No work center is assigned The work center has no capacity data Capacity calculation is deactivated at network header level
Question
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined. What are the possible reasons?
Options
- AA work center has not been assigned to the activity
- BThe work center does not contain any available capacity data
- CThe wrong activity type category is entered in the activity
- DThe indicator that calculates capacity requirements is deactivated in the header of the network
- EThe capacity distribution key field is empty
Explanation
Capacity requirements cannot be calculated if: No work center is assigned The work center has no capacity data Capacity calculation is deactivated at network header level