Question
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
Options
- AThe formula for costing in the work center is incorrect
- BThe activity output price for the activity type and cost center assigned to the work center is not
- CThe duration is missing in the activity
- DThe Determine Costs indicator in the network header rules out planned cost calculation
- EIntegrated planning for the network is active
Unlock C_TS412_2021 to see the answer