C_TS412_2021 · Question #85

You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the…

The correct answer is A. The formula for costing in the work center is incorrect B. The activity output price for the activity type and cost center assigned to the work center is not D. The Determine Costs indicator in the network header rules out planned cost calculation. Planned costs are calculated for internally-processed network activities based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. If any of these factors…

Costs and Revenues in Project Systems

Question

You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question

Options

  • AThe formula for costing in the work center is incorrect
  • BThe activity output price for the activity type and cost center assigned to the work center is not
  • CThe duration is missing in the activity
  • DThe Determine Costs indicator in the network header rules out planned cost calculation
  • EIntegrated planning for the network is active

How the community answered

(32 responses)
  • A
    59% (19)
  • C
    28% (9)
  • E
    13% (4)

Explanation

Planned costs are calculated for internally-processed network activities based on the formula for costing in the work center, the activity output price for the activity type and cost center assigned to the work center, and the duration of the activity. If any of these factors are missing or incorrect, no planned costs will be displayed. The Determine Costs indicator in the network header also controls whether planned costs are calculated or not. If it is not set, no planned costs will be

Topics

#planned costs#work center formula#activity type pricing#integrated planning