nerdexam
SAP

C_TS412_2021 · Question #59

C_TS412_2021 Question #59: Real Exam Question with Answer & Explanation

The correct answer is B. Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.. This is how earliest dates and latest dates of activities are scheduled in the SAP Project System. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling. Forward scheduling is a method of scheduling activities from the start date of the proje

Question

How are earliest dates and latest dates of activities schedule?

Options

  • AEarliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.
  • BEarliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.
  • CEarliest dates and latest dates are scheduled by forward scheduling.
  • DEarliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest

Explanation

This is how earliest dates and latest dates of activities are scheduled in the SAP Project System. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling. Forward scheduling is a method of scheduling activities from the start date of the project to the end date. Backward scheduling is a method of scheduling activities from the end date of the project to the start date. The earliest dates are determined by forward scheduling and the latest dates are determined by backward scheduling. This ensures that the activities are scheduled within the project duration and that any slack time is distributed evenly

Community Discussion

No community discussion yet for this question.

Full C_TS412_2021 Practice