- Question #1
Your organization uses Project Professional 2013. A senior stakeholder in a project asks you to determine when a task is over budget by comparing the baseline cost of a task to the...
- Question #2
You are a project manager, and you successfully complete a server consolidation project for one of your data centers. You use Project Standard 2013 to plan and track the work. Your...
- Question #3
You are project manager who uses Project Professional 2013. Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upco...
- Question #4
You are a project manager who uses Project Standard 2013. You have been told to build multiple project files for a program. You need to have all of your projects start with auto sc...
- Question #5
You are a resource manager who uses Project Standard 2013. You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organi...
- Question #6
You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remain...
- Question #7
You are a project manager who uses Project Standard 2013, and your task list includes a flag field that indicates, with Yes or No, if a non-summary task represents a physical deliv...
- Question #8
You are a project manager who uses Project Standard 2013. Your manager wants you to plan an office move. You have a project schedule from a prior office move named "OfficeMove.mpp"...
- Question #9
You are a project manager who uses Project Professional 2013. A senior stakeholder asks you to update your project to reflect your organization's scheduled two- week closure. You n...
- Question #10
You are a project manager for an organization that uses Project Standard 2013. You add shortcuts on the Quick Access Toolbar to your most frequently used commands. Your manager is...
- Question #11
You are a project manager, and your organization uses Project Standard 2013. You have created a non-working day in a resource's calendar; however, the HR department notifies you th...
- Question #12
You are a project manager who uses Project Professional 2013. All resources in your project schedule have availability of 8 hours per day. You notice that several of the resources...
- Question #13
You manage a project for an organization that relies heavily on schedule baselines in Project Standard 2013. A change is approved for an in-progress project which you manage. You e...
- Question #14
You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to calculate Variance at Completion (VAC). You have already set Baseline2. What should you...
- Question #15
You are a manager for an organization that uses Project Professional 2013. A critical project shows average finish variance values between 5-10 days for the tasks. You need to inte...
- Question #16
You are a project manager who uses Project Professional 2013. When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the criti...
- Question #17
You manage a project by using Project Professional 2013. A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kep...
- Question #18
You manage a project by using Project Professional 2013. The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed. You ne...
- Question #19
You manage a project and use Project Professional 2013 to track your project schedule. One of several resources assigned to a fixed-unit, effort-driven, five-day task is assigned a...
- Question #20
You are a project manager in an organization that uses Project Server 2013. All project managers have permission to edit all projects. You edit a project in Project Web App (PWA),...
- Question #21
You are a program manager who uses Project Server 2013 and Project Professional 2013. You have administrative rights. Your project managers create subprojects for your program-leve...
- Question #22
You are a project manager who uses Project Professional 2013. After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the ori...
- Question #23
You manage a project for an organization that uses Project Professional 2013. You reset the baseline for some selected tasks. After the baseline has been updated with the new value...
- Question #24
Your company uses Project Professional 2013. You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test...
- Question #25
Your company uses Project Professional 2013. You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of t...
- Question #26
Your company uses Project Professional 2013. You are a program manager who has a master project created for your program. Currently you are seeing the critical path for each indepe...
- Question #27
You are a project manager in an organization that uses Project Professional 2013. You are managing a project, which involves the construction of a new shopping mall. The shopping m...
- Question #28
You are managing a project by using Project Professional 2013. Your project schedule contains 1000 tasks which are in outline format. You discover that the Design summary task is l...
- Question #29
Your organization uses Project Professional 2013. A senior stakeholder informs you that your project start date is delayed and gives you a new start date. You need to change the pr...
- Question #30
You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create two manually sch...
- Question #31
You are using Project Standard 2013. Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project....
- Question #32
Your company uses Project Professional 2013. You have two projects, Project 1 and Project 2, as well as a resource pool to contain all of the resources. You use resource leveling a...
- Question #33
Your organization uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. As you build the task breakdown, you notice a potenti...
- Question #34
You are a project manager who uses Project Professional 2013. You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013...
- Question #35
You are a project manager who uses Project Standard 2013. You work on a project that requires you to generate many documents. Each task in your project plan must have a document as...
- Question #36
You are a project manager for an organization that uses Project Professional 2013. You manage a critical project across multiple regions. All information regarding the project must...
- Question #37
You are a project manager for a company that uses Project Professional 2013. You are responsible for communicating the progress of your projects every month. Your company provides...
- Question #38
You are a project manager who uses Project Professional 2013. You have created a project which involves three other colleagues who are also using Project Professional 2013. You and...
- Question #39
You are a project manager who uses Project Professional 2013. You work in a software development project, which is in progress and has reached 60% of actual progress. Your company...
- Question #40
You are a project manager who uses Project Professional 2013. You manage a project, which involves three other colleagues who also have experience in Project Professional 2013. You...
- Question #41
You are an independent project manager who uses Project Professional 2013. You work on multiple projects for different customers, and you use one project to manage all of their tas...
- Question #42
You are a project manager for a software development company that uses Project Professional 2013. For managing projects, your company has its own specialized processes, all of whic...
- Question #43
You are a project manager who uses Project Professional 2013. You manage a critical project, which involves many team members. You are the only team member who has Project Professi...
- Question #44
You are a Project Manager who uses Project Professional 2013. You manage a critical project, which is synchronized with a Microsoft SharePoint Task List. One of your team members h...
- Question #47
You are an independent project manager who uses Project Professional 2013. You work in multiple projects for different customers and use one project to manage all their tasks. You...
- Question #48
Your organization uses Project Professional 2013 and Microsoft SharePoint 2013. You are responsible for a project with resources in different offices. All offices share the same Sh...
- Question #49
You are a project manager who uses Microsoft Excel 2013. Your company decides to migrate all of the current projects in Microsoft Excel 2013 to Project Professional 2013. They allo...
- Question #50
You are a project manager who uses Project Professional 2013. Your organization has been working with a new status report model for the last month. This new status report is create...
- Question #51
You are a project manager who uses Project Professional 2013. Your organization migrates all project plans from Microsoft Excel to Project Professional 2013. One of the directors o...
- Question #52
Your company uses Project Professional 2013. An organization with project managers of varying expertise wants a simple, standard view that displays overall project status. You need...