You manage a project for an organization that uses Project Professional 2013. You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize…

The correct answer is C. Reset the baseline for the selected tasks and select the Roll up baselines to all summary. See the full explanation below for the reasoning.

Question

You manage a project for an organization that uses Project Professional 2013. You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct. You need to resolve this problem. What should you do?

Options

  • AUpdate the summary tasks manually with the new duration values.
  • BChange all task durations to the same denomination values, such as days, weeks, or months.
  • CReset the baseline for the selected tasks and select the Roll up baselines to all summary
  • DReset the summary tasks to manual scheduling.

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    80% (28)
  • D
    11% (4)