Microsoft
74-343 · Question #23
74-343 Question #23: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #23. The question stem and answer options stay visible for context.
Question
You manage a project for an organization that uses Project Professional 2013. You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct. You need to resolve this problem. What should you do?
Options
- AUpdate the summary tasks manually with the new duration values.
- BChange all task durations to the same denomination values, such as days, weeks, or months.
- CReset the baseline for the selected tasks and select the Roll up baselines to all summary
- DReset the summary tasks to manual scheduling.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.