74-343 · Question #25
74-343 Question #25: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #25. The question stem and answer options stay visible for context.
Question
Your company uses Project Professional 2013. You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of tasks with predecessors: You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule. You need to determine what the results are to the schedule when inactivating Task C. How should you answer?
Exhibit
Options
- AThe finish date is reduced by four working days, cost remains unchanged, and baseline cost
- BThe finish date is reduced by five working days, cost remains unchanged, and baseline cost
- CThe finish date is reduced by six working days, cost is reduced by $400, and baseline cost is
- DThe finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost
- EThe finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost