74-343 · Question #92
74-343 Question #92: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #92. The question stem and answer options stay visible for context.
Question
You are managing a project using Project Professional 2013. Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations. You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes. What should you do?
Options
- AClick the BA1 resource and scroll to the end of the project.
- BClick View, check Details, select Resource Form then click on the BA1 resource.
- CClick View, check Details, select Task Form then click on the BA1 resource.
- DRight-click the BA1 resource and select Information.