74-343 · Question #1
74-343 Question #1: Real Exam Question with Answer & Explanation
Sign in or unlock 74-343 to reveal the answer and full explanation for question #1. The question stem and answer options stay visible for context.
Question
Your organization uses Project Professional 2013. A senior stakeholder in a project asks you to determine when a task is over budget by comparing the baseline cost of a task to the cost. Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost is greater than the cost. You write a formula to display the indicator, but it only displays for normal tasks and not for summary tasks. You need to make the indicator display for summary tasks. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Options
- AWithin the Custom Field, set Calculation for task and group summary rows to Use Formula.
- BWithin the Custom Field, set Calculation for task and group summary rows to Maximum.
- CWithin the Graphical Indicators dialog box, check the Import Indicator Criteria button.
- DWithin the Graphical Indicators dialog box, check Summary rows inherit criteria from