74-343 · Question #2

74-343 Question #2: Real Exam Question with Answer & Explanation

The correct answer is D. Open the plan and save the plan as a Project Template.. See the full explanation below for the reasoning.

Question

You are a project manager, and you successfully complete a server consolidation project for one of your data centers. You use Project Standard 2013 to plan and track the work. Your manager wants you to begin similar projects on two other data centers. You need to create a template based on the plan you used to manage the first data center consolidation project. You need to ensure that the template has all baseline and actual data values removed. What should you do?

Options

  • AWithin Microsoft Windows Explorer, create a copy of the original project plan and rename
  • BOpen the plan and use the Move Project button to set the start date to the start of the new
  • COpen the plan and reset the percent complete for each task to 0.
  • DOpen the plan and save the plan as a Project Template.
  • EOpen the plan, and copy and paste all of the task information into a new plan.