You are project manager who uses Project Professional 2013. Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project. The…

The correct answer is C. Open the tasks directly from the SharePoint site into Project Professional 2013. See the full explanation below for the reasoning.

Question

You are project manager who uses Project Professional 2013. Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project. The task list contains over 100 items. You need to create a project based on the tasks in the SharePoint list in the most efficient manner. What should you do?

Options

  • AExport the tasks into Microsoft Excel and then import the Excel file into Project Professional
  • BEdit the Project Summary Task hyperlink column to point to the SharePoint task list and click
  • COpen the tasks directly from the SharePoint site into Project Professional 2013.
  • DCopy and paste the tasks from SharePoint into Project Professional 2013.

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    84% (27)
  • D
    3% (1)