74-343 · Question #62
You are a program manager for a complex software development project. You use Project Professional 2013 to manage your project. Your resources work on many different projects across the program, and…
The correct answer is A. Set the priority of Project A to 1000 and the priority of Project B to 500, Set the Leveling. See the full explanation below for the reasoning.
Question
You are a program manager for a complex software development project. You use Project Professional 2013 to manage your project. Your resources work on many different projects across the program, and you need to resolve resource over allocations. Your project team uses a resource pool to manage resources. Resource1 has been assigned to assist on a project that is on the critical path. After assigning Resource2 to the task, you notice that Resource1 is over allocated during the month of November. Project A, which is on critical path, takes priority over Project B, which Resource1 is also assigned to. Using resource leveling in Project Professional 2013, you need to resolve the over allocation for Resource1 for the month of November only. What should you do?
Options
- ASet the priority of Project A to 1000 and the priority of Project B to 500, Set the Leveling
- BSet the priority of Project A to 500 and the priority of Project B to 1000. Set the Leveling
- CSet the priority of Project A to 1000 and the priority of Project B to 500.
- DSet the priority of Project A to 500 and the priority of Project B to 1000.
How the community answered
(24 responses)- A75% (18)
- B13% (3)
- C4% (1)
- D8% (2)
Community Discussion
No community discussion yet for this question.