74-343 · Question #56
You are a project manager who uses Project Standard 2013. You manage a software development project and have acquired two additional resources to assist in the completion of tasks that are on the…
The correct answer is C. Select the Resource Sheet and change Max Units to the following. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Standard 2013. You manage a software development project and have acquired two additional resources to assist in the completion of tasks that are on the critical path. Both resources are also assigned to participate in other projects. Resource1 is available 50% and Resource2 is available 75%. You need to add the resources with their availability to the project schedule and make any allocation problems visible. What should you do?
Options
- AAssign the two resources to the tasks with the following units:
- BSelect the Resource Sheet and change Max Units to the following:
- CSelect the Resource Sheet and change Max Units to the following:
- DAssign the two resources to the tasks with the following units:
How the community answered
(27 responses)- A11% (3)
- B7% (2)
- C78% (21)
- D4% (1)