Question
You are a resource manager who uses Project Standard 2013. You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resource needs to pass an annual exam in order to work on construction sites. You need to set up a method that allows you to pick the renewal month for each resource. What should you do?
Options
- ARename the Resource Text1 Custom field to Exam Expiration Date.
- BUse the Organizer to copy the Resource Finish1 Custom field from the Global.mpt.
- CRename the Resource Date1 Custom field to Exam Expiration Date.
- DRename the Resource Month1 Custom field to Exam Expiration Date.
- ERename the Resource Flag1 Custom field to Exam Expired Date.