You are a resource manager who uses Project Standard 2013. You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resourc

The correct answer is C. Rename the Resource Date1 Custom field to Exam Expiration Date.. See the full explanation below for the reasoning.

Question

You are a resource manager who uses Project Standard 2013. You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resource needs to pass an annual exam in order to work on construction sites. You need to set up a method that allows you to pick the renewal month for each resource. What should you do?

Options

  • ARename the Resource Text1 Custom field to Exam Expiration Date.
  • BUse the Organizer to copy the Resource Finish1 Custom field from the Global.mpt.
  • CRename the Resource Date1 Custom field to Exam Expiration Date.
  • DRename the Resource Month1 Custom field to Exam Expiration Date.
  • ERename the Resource Flag1 Custom field to Exam Expired Date.

How the community answered

(31 responses)
  • B
    3% (1)
  • C
    81% (25)
  • D
    6% (2)
  • E
    10% (3)