nerdexam
Microsoft

74-343 · Question #6

You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You n

The correct answer is B. Open each resource and amend the working time on each resource's calendar.. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?

Options

  • AOpen each resource and set a recurring exception to reflect the non-working days.
  • BOpen each resource and amend the working time on each resource's calendar.
  • COpen each resource and set their Resource Availability units to 50%.
  • DOpen each resource and use the Resource information dialog box to create a new calendar.

How the community answered

(13 responses)
  • B
    85% (11)
  • C
    8% (1)
  • D
    8% (1)

Community Discussion

No community discussion yet for this question.

Full 74-343 Practice