74-343 · Question #6
You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You n
The correct answer is B. Open each resource and amend the working time on each resource's calendar.. See the full explanation below for the reasoning.
Question
You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?
Options
- AOpen each resource and set a recurring exception to reflect the non-working days.
- BOpen each resource and amend the working time on each resource's calendar.
- COpen each resource and set their Resource Availability units to 50%.
- DOpen each resource and use the Resource information dialog box to create a new calendar.
How the community answered
(13 responses)- B85% (11)
- C8% (1)
- D8% (1)