74-343 · Question #6

You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You…

The correct answer is B. Open each resource and amend the working time on each resource's calendar. See the full explanation below for the reasoning.

Question

You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?

Options

  • AOpen each resource and set a recurring exception to reflect the non-working days.
  • BOpen each resource and amend the working time on each resource's calendar.
  • COpen each resource and set their Resource Availability units to 50%.
  • DOpen each resource and use the Resource information dialog box to create a new calendar.

How the community answered

(13 responses)
  • B
    85% (11)
  • C
    8% (1)
  • D
    8% (1)

Community Discussion

No community discussion yet for this question.