Microsoft
74-343 · Question #63
You are a project manager for an organization that uses Project Professional 2013. You are planning a project schedule that starts on March 1 and lasts four months. However, the sponsor now asks…
Sign in or unlock 74-343 to reveal the answer and full explanation for question #63. The question stem and answer options stay visible for context.
Question
You are a project manager for an organization that uses Project Professional 2013. You are planning a project schedule that starts on March 1 and lasts four months. However, the sponsor now asks that the project be delayed to have a finish date of December 31.
Options
- AChange all task constraint types to Start no later than.
- BChange the Schedule from field to Project Finish Date.
- CChange the project Start date so that the project will finish on December 31.
- DChange all task constraint types to As late as possible.
- EChange the project Finish date so that the project will finish on December 31.
Unlock 74-343 to see the answer
You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.