74-343 · Question #63

74-343 Question #63: Real Exam Question with Answer & Explanation

The correct answer is B. Change the Schedule from field to Project Finish Date. D. Change all task constraint types to As late as possible. E. Change the project Finish date so that the project will finish on December 31.. See the full explanation below for the reasoning.

Question

You are a project manager for an organization that uses Project Professional 2013. You are planning a project schedule that starts on March 1 and lasts four months. However, the sponsor now asks that the project be delayed to have a finish date of December 31.

Options

  • AChange all task constraint types to Start no later than.
  • BChange the Schedule from field to Project Finish Date.
  • CChange the project Start date so that the project will finish on December 31.
  • DChange all task constraint types to As late as possible.
  • EChange the project Finish date so that the project will finish on December 31.