nerdexam
Microsoft

74-343 · Question #63

You are a project manager for an organization that uses Project Professional 2013. You are planning a project schedule that starts on March 1 and lasts four months. However, the sponsor now asks…

Sign in or unlock 74-343 to reveal the answer and full explanation for question #63. The question stem and answer options stay visible for context.

Question

You are a project manager for an organization that uses Project Professional 2013. You are planning a project schedule that starts on March 1 and lasts four months. However, the sponsor now asks that the project be delayed to have a finish date of December 31.

Options

  • AChange all task constraint types to Start no later than.
  • BChange the Schedule from field to Project Finish Date.
  • CChange the project Start date so that the project will finish on December 31.
  • DChange all task constraint types to As late as possible.
  • EChange the project Finish date so that the project will finish on December 31.

Unlock 74-343 to see the answer

You've previewed enough free 74-343 questions. Unlock 74-343 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full 74-343 Practice