You are a project manager and have built a project plan by using Project Professional 2013. Your project plan has both fixed duration and fixed work tasks. You have been asked to denote key existing…
The correct answer is C. Set the Duration column to 0 to set the task as a milestone. See the full explanation below for the reasoning.
Question
You are a project manager and have built a project plan by using Project Professional 2013. Your project plan has both fixed duration and fixed work tasks. You have been asked to denote key existing tasks as milestones in the Gantt view. What should you do?
Options
- AFormat the bar styles in the Gantt view to denote the tasks as milestones.
- BEnter the word Milestone in the Task Duration column to set the task as a milestone.
- CSet the Duration column to 0 to set the task as a milestone.
- DNavigate to View, Text Styles, select Milestones, and then select the black diamond.
How the community answered
(31 responses)- A13% (4)
- B10% (3)
- C74% (23)
- D3% (1)