74-343 · Question #65
Your company uses Project Professional 2013, and you are setting up an initial planning schedule. You need to set each task duration as estimated, until the estimate is confirmed by the assigned…
The correct answer is A. Select the estimated check box. See the full explanation below for the reasoning.
Question
Your company uses Project Professional 2013, and you are setting up an initial planning schedule. You need to set each task duration as estimated, until the estimate is confirmed by the assigned resource. What should you do?
Options
- ASelect the estimated check box.
- BUse a task custom field and set the Roll task down to assignment check box.
- CEnter the duration suffixed with -ed for estimated days.
- DSet the task to manually scheduled.
- EUse an assignment custom field and set the Roll assignment up to task check box.
How the community answered
(69 responses)- A75% (52)
- B14% (10)
- C1% (1)
- D6% (4)
- E3% (2)